We are pleased to inform the community that the first stage of the paving project has been successfully completed, reaching a total rehabilitated area of 625 m², with a final investment of $1,378,250.00 pesos. This progress addresses a priority need for improving internal circulation and road safety in our complex.
📌 First phase completed
Rehabilitated area:625 m²
Investment made:$1,378,250.00 pesos
🚧 Next Phase 2: continuation of the project
Following up on the improvement of our roadways, phase 2 includes the rehabilitation of an additional 375 m², with a planned investment of $826,500.00 pesos. This work will be carried out in continuity with the already rehabilitated section, ensuring uniformity in the surface condition and quality of the material used.
➡️ Details of Phase 2
Estimated area:375 m²
Planned investment:$826,500.00 pesos
Start date: will be announced in the coming days through this same medium.

We will continue to inform through this medium about each advance of the project, so that everyone can follow the stages and results.