Paving Project in Puerto Aventuras

October 9, 2025 by
Paving Project in Puerto Aventuras
ASOCIACION DE COLONOS PROPIETARIOS Y FIDEICOMISARIOS DE PUERTO AVENTURAS, Cecilia García Casteiro
| No comments yet

The Puerto Aventuras Settlers Association is pleased to inform the entire community that, after an evaluation and selection process, the paving project has been awarded to the company La Roca Azul Constructora S.A. de C.V., headed by Engineer Roberto Benito, a member of our own community.

This important project includes a first stage of work on 600 m², with an investment of $1,322,400 pesos. The estimated duration of the work is 50 days and, shortly, the official start date will be confirmed.

🏗️ Transparent evaluation process

To guarantee the quality and seriousness of this project, the selected proposal was evaluated along with two other options, in a process that lasted a month.

The review and analysis were carried out by the Association's Board of Directors, the Director General and the Supervisory Committee, who took into account technical, financial and proven experience aspects.

📍 Work area

The first stage will be developed in a priority section for the improvement of the internal roads of Puerto Aventuras.

👉 In this blog you can find a sketch of the area where the work will be carried out, so that all residents are informed about the development of the work.

🤝 An important step for our community

This project represents a significant advance in the improvement of the infrastructure of our complex and responds to a priority need that has been raised by the neighbors for some time. Thanks to the joint effort, today we are beginning to see this goal materialize.

We thank the entire community for their trust in the development of this project that is so relevant for everyone.



🛣  Update October 23, 2025

The Secretariat of Infrastructure and Public Works of the Government of Playa del Carmen has issued the official authorization for the execution of the paving project in Puerto Aventuras. This step allows the project to move forward with the start of construction on October 23, according to the established plan and in coordination with the contracted company. We will continue to share progress updates through this space.  